Public Procurement Rules, 2026 (PPRA Rules 2026)

The Public Procurement Rules, 2026 (S.R.O. 1658(I)/2026 dated 28 September 2026) replace the 2004 Rules and regulate Federal procurement planning, EPADS, tendering, evaluation, contract management and grievance redressal.

Overview

The Public Procurement Rules, 2026 were notified by the Government of Pakistan, Cabinet Secretariat (Cabinet Division), through S.R.O. 1658(I)/2026 dated 28 September 2026 under section 26 of the Public Procurement Regulatory Authority Ordinance, 2002. The Rules came into force at once and apply to public procurements made by Federal Government procuring agencies within or outside Pakistan.

The Rules establish the framework for procurement planning, EPADS, procurement cells and evaluation committees, publication and response times, bidder eligibility, procurement methods and financial thresholds, bidding and evaluation, bid security, contract management, inspection, transparency, grievance redressal and dispute resolution. They contain 69 Rules and Schedule I. Rule 68 preserves the 2004 Rules for procurement proceedings initiated before commencement, while Rule 69 repeals the 2004 Rules.

Key Highlights

  • S.R.O. 1658(I)/2026 dated 28 September 2026; Gazette of Pakistan, Extraordinary, Part II.
  • Made by the Federal Government under section 26 of the Public Procurement Regulatory Authority Ordinance, 2002 (XXII of 2002); came into force at once.
  • Contains 69 Rules and Schedule I; applies to public procurements of Federal Government procuring agencies within or outside Pakistan.
  • Requires public procurement through the E-Pak Acquisition and Disposal System (EPADS).
  • Places overall procurement control and supervision with the Principal Accounting Officer or Head of Procuring Agency; requires annual procurement planning and a Procurement Cell.
  • Provides for Bid Evaluation Committees for procurements up to Rs. 2 billion, third-party validation above Rs. 500 million and up to Rs. 2 billion, and external bid evaluation above Rs. 2 billion.
  • Procurements exceeding Rs. 200,000 are to be published on EPADS and the PPRA website; opportunities exceeding Rs. 5 million also require publication in at least two national newspapers, one English and one Urdu.
  • Minimum response time is 10 days for national competitive bidding and 20 days for international competitive bidding; the specified request-for-quotation method has a minimum 24-hour response time.
  • Alternative methods include shopping below Rs. 200,000, request for quotations above Rs. 200,000 but below Rs. 700,000, and gallop tendering between Rs. 700,000 and Rs. 2 million.
  • Bid security may not exceed 5% for procurements up to Rs. 250 million and 2% for procurements above Rs. 250 million; a bid security declaration applies where bid security is not required.
  • Provides for electronic bid opening and live broadcasting above Rs. 500 million for goods and services and Rs. 1 billion for works.
  • For specified significant procurements above Rs. 1 billion or cross-border deliveries, Rule 61 requires third-party inspection or evaluation arrangements.
  • Rule 65 sets out pre-contract grievance procedures, complaint periods, GRC decision timeframe and appeal to the Authority’s Appellate Committee.
  • Rule 68 provides that procurement proceedings initiated before commencement continue under the Public Procurement Rules, 2004; Rule 69 repeals the 2004 Rules.

Detailed Explanation

The Public Procurement Rules, 2026, commonly referred to as the PPRA Rules, 2026, establish the updated regulatory framework for public procurement by Federal Government procuring agencies. The Rules were notified through S.R.O. 1658(I)/2026 dated 28 September 2026, issued by the Cabinet Secretariat (Cabinet Division), under section 26 of the Public Procurement Regulatory Authority Ordinance, 2002. They came into force at once and repealed the Public Procurement Rules, 2004, subject to the transition provision for procurement proceedings initiated before commencement.

Issuing Authority, Notification Date and Legal Basis

The Rules were notified by the Government of Pakistan, Cabinet Secretariat (Cabinet Division), through S.R.O. 1658(I)/2026 dated 28 September 2026. The notification was published in the Gazette of Pakistan, Extraordinary, Part II, at Islamabad on the same date.

The Federal Government made the Rules in exercise of the powers conferred by section 26 of the Public Procurement Regulatory Authority Ordinance, 2002 (Ordinance XXII of 2002). Rule 1 provides that the Rules come into force at once. The Gazette instrument contains 69 Rules and Schedule I.

Scope and Applicability of the PPRA Rules, 2026

Rule 3 provides that, save as otherwise provided, the Rules apply to all public procurements made by procuring agencies of the Federal Government, whether within or outside Pakistan. They therefore govern Federal Government procuring agencies and are not, merely by their own terms, a general replacement for the separate procurement rules of every Provincial Government.

The Rules cover procurement of goods, works and services and regulate the process from planning and publication of procurement notices to bid evaluation, contract award, contract administration, grievance redressal and contract closure. They should be read with the PPRA Ordinance, 2002, regulations issued by the Authority, standard bidding documents and applicable Federal Government policies.

Fundamental Principles of Public Procurement

Rule 4 requires procuring agencies to conduct procurement in a fair and transparent manner, secure value for money, and ensure that the process is efficient and economical. The Rules also address international and inter-governmental commitments, language of procurement documentation, integrity pacts and electronic procurement.

Where a procurement obligation of the Federal Government under an international treaty, agreement with a State or States, or agreement with an international financial institution conflicts with the Rules, Rule 5 provides that the relevant obligation prevails to the extent of the conflict. Procurement communications and documents are generally to be in Urdu or English, subject to the limited provisions for local-language use and retention of the original record.

Electronic Procurement Through EPADS

Rule 8 requires procuring agencies to carry out public procurement through the E-Pak Acquisition and Disposal System (EPADS). The system is integrated into publication, receipt and opening of bids, clarification of bidding documents, communication with bidders, procurement records, evaluation and contract-management processes.

The Rules require procurement information and prescribed records to be made available through EPADS. Procuring agencies should ensure that officers assigned procurement functions are trained and able to use the system, and that procurement actions are properly recorded electronically.

Responsibility of the Principal Accounting Officer or Head of Procuring Agency

Under Rule 9, the Principal Accounting Officer (PAO) or Head of Procuring Agency has overall control and supervision over public procurement conducted by the procuring agency. Responsibilities include ensuring compliance with the Ordinance, Rules and regulations, approving the annual procurement plan, establishing a Procurement Cell and constituting Bid Evaluation Committees.

The PAO or Head of Procuring Agency decides the size, location and structure of the Procurement Cell in light of the agency’s procurement requirements and the availability of trained officers. Where procurement activity does not justify a separate cell, a public officer may be nominated to perform its functions.

Procurement Cell and Evaluation Committees

Procurement Cell

Rule 10 requires a Procurement Cell comprising officers with relevant qualifications or experience and accreditation by the Authority. Officers who are not yet accredited may continue to serve, subject to acquiring accreditation within twelve months from the date on which the Procurement Cell is notified.

The Cell’s functions include consolidating requisitions, conducting market analysis, checking budget availability, preparing the annual procurement plan, developing specifications and bidding documents, publishing notices, receiving and safeguarding bids, coordinating evaluation, communicating outcomes through EPADS, monitoring contract performance and maintaining complete procurement records.

Bid Evaluation Committee

Rule 11 provides for a Bid Evaluation Committee with an odd number of members from within the procuring agency for procurements with an estimated value up to Rs. 2 billion. At least one member must have relevant qualifications or experience and Authority accreditation. Where an accredited member is unavailable within the agency, an unaccredited member may be appointed subject to acquiring accreditation within the prescribed twelve-month period.

Third-Party Validation and External Evaluation

Rule 12 requires third-party validation for procurements above Rs. 500 million and up to Rs. 2 billion. Validation covers preparation of specifications and bidding documents, technical evaluation where applicable, and final evaluation.

For procurements exceeding Rs. 2 billion, Rule 13 provides for an External Bid Evaluation Committee with at least two-thirds of its members from outside the procuring agency, drawn from the Authority’s pre-qualified pool or firm. These provisions create additional review arrangements for high-value procurement.

Annual Procurement Planning and Estimated Value

Rule 15 requires procuring agencies to plan proposed procurements in detail, determine realistic requirements in light of available resources and delivery timelines, and publish an annual procurement plan on EPADS and the PPRA website in the Authority’s prescribed format. Procurement is to be conducted in accordance with the approved plan. Where a method other than open competitive bidding is used, justification must be recorded; the plan may be revised for emerging requirements with written reasons.

Rule 16 requires the estimated value to be calculated on the total amount payable and, for works, to include both the cost of the works and the estimated value of supplies needed to execute them. The value is calculated when the procurement notice is issued. A procuring agency must not artificially divide procurement to avoid financial thresholds or restrict competition. Procurement may, however, be packaged into lots where this is expected to achieve better overall value or support sustainable procurement goals; the values of all lots must be aggregated for threshold purposes.

Specifications, Publication and Response Time

Specifications and Bidding Documents

Rule 17 requires specifications to allow the widest possible competition and not favour or disadvantage a particular bidder. Specifications should ordinarily be generic and may describe the purpose, requirements, functional and performance characteristics, processes, materials, inspection and testing requirements and applicable standards. A brand name or catalogue reference may be used only in the limited circumstances described in the Rule, with written justification and the words “or equivalent” where required.

Publication of Procurement Opportunities

Under Rule 18:

  • Procurements exceeding Rs. 200,000, including requests for quotation, are to be published on EPADS and the PPRA website, as well as on the procuring agency’s website where it has one.
  • Procurement opportunities exceeding Rs. 5 million are also to be published in print media or newspapers having wide circulation, principally in at least two national dailies—one English and one Urdu.
  • Published information must be complete for its purpose and remain available until the closing date for submission of bids.

Minimum Response Time

Rule 19 provides a minimum response time of 10 days for national competitive bidding and 20 days for international competitive bidding, calculated from publication of the procurement notice on EPADS. For procurement through request for quotations under Rule 32(1)(b), the response time must not be less than 24 hours. The procuring agency must also consider the complexity, availability and urgency of the procurement when setting the response period.

Eligibility, Pre-qualification and Blacklisting of Bidders

Rules 21 to 25 address bidder eligibility, pre-qualification, the pre-qualification process, qualification and disqualification, and blacklisting. Eligibility includes technical competence, financial resources, equipment, personnel, managerial capability, experience and past performance, together with legal capacity and other conditions prescribed by the Rules and bidding documents.

The Rules require pre-qualification to be completed within a reasonable time specified in the pre-qualification documents. Reasons for non-qualification are to be communicated to unsuccessful applicants. A bidder may be disqualified where materially inaccurate, incomplete or false eligibility information is knowingly submitted, or required information is not provided. Blacklisting proceedings are to follow the Authority’s applicable Mechanism for Blacklisting and Debarment Regulations, 2024.

Methods of Procurement and Financial Thresholds

Rule 26 identifies open competitive bidding as the principal procurement method, subject to the alternative methods and other specific provisions of the Rules. The framework also provides for single-stage two-envelope bidding for commodities listed in Schedule I, framework agreements, requests for proposals for consultancy services under the relevant regulations, and gallop tendering.

Method / RequirementThreshold or Main Condition
Shopping without request for quotationsBelow Rs. 200,000; complete procurement record must be available on EPADS.
Shopping through request for quotationsMore than Rs. 200,000 but less than Rs. 700,000; at least three quotations from the specified sources and selection of the lowest-priced supplier.
Gallop tenderBetween Rs. 700,000 and Rs. 2 million; minimum five-day response period and single-stage, one-envelope procedure.
Publication on EPADS and PPRA websiteAll procurements exceeding Rs. 200,000, including requests for quotation.
Publication in national newspapersProcurement opportunities exceeding Rs. 5 million; at least two national dailies, one English and one Urdu.

Rule 32 also provides for direct contracting and negotiated tendering in specified circumstances, including certain proprietary or exclusive supplies, compatibility requirements, qualifying repeat orders, Government-fixed prices and cases of extreme urgency not attributable to the procuring agency. The conditions and written-justification requirements in the Rule must be satisfied before using an alternative method.

Framework Agreements and Procurement of Second-Hand Goods

Rule 30 allows open and closed framework agreements for common-use goods, works or services where requirements recur but the timing or exact quantity is not known in advance. A closed framework agreement may have a maximum duration of one year, while an open framework agreement may have a maximum duration of three years. The Rules prescribe how call-off orders or secondary procurement processes are used under each arrangement.

Rule 33 permits procurement of second-hand goods through EPADS where this provides an economical and efficient means of meeting the agency’s requirements. The procuring agency must consider age and condition, expected life, price, risk, warranty, maintenance and safety. A technical committee from outside the procuring agency is to provide third-party validation, and inspection or verification is required before acceptance.

Bidding, Bid Security and Evaluation

Rules 34 to 50 deal with bidding documents, reservations and preferences, bid security, bid validity, clarifications, extensions, submission and opening of bids, evaluation criteria, bid evaluation, abnormally low bids, rejection or cancellation, re-bidding, publication of evaluation results and acceptance of bids.

Rule 36 allows the procuring agency to require bid security not exceeding 5% of the estimated value for procurements up to Rs. 250 million and not exceeding 2% for procurements above Rs. 250 million. Where bid security is not required, the bidder is to submit a bid security declaration in the Authority’s prescribed standard format.

Bids are to be received and opened through EPADS. The submission and opening date is the same, and opening is to take place not less than 30 minutes after the submission deadline. For procurements exceeding Rs. 500 million in goods and services and Rs. 1 billion in works, Rule 40 provides for live broadcasting of bid opening on national media or the procuring agency’s website or digital channels.

Evaluation must follow the criteria and conditions stated in the bidding documents. A bid may be examined as abnormally low only after the bidder has been asked through EPADS to provide a written clarification and price analysis, and the procuring agency has considered the bidder’s response. The Rules also regulate single responsive bids, performance guarantees and safeguards before contract award.

Contract Management, Inspection and Completion

Rules 51 to 62 address performance guarantees, letters of credit, restrictions on negotiations, confidentiality, on-account payments, entry into force of procurement contracts, procurement records, public access and transparency, contract managers, contract performance evaluation, inspection of goods and evaluation of services, and closing of contracts.

Rule 58 provides for appointment of a Contract Manager, while Rule 59 sets out the Contract Manager’s duties. Rule 60 addresses contract performance evaluation and reporting. For significant procurements exceeding Rs. 1 billion or procurements involving cross-border deliveries, Rule 61 requires third-party pre-shipment inspection of goods and evaluation of services, subject to the detailed arrangements and exceptions in that Rule.

Rule 62 provides for the issue of an overall delivery or taking-over certificate through EPADS within 30 days after final taking over or completion. Where a defect-liability or maintenance period applies, the relevant certificate is to be issued within 30 days after its expiry. The Rule also addresses payment of the final bill and closure of the contract for audit purposes.

Socio-economic Development and Environmental Objectives

Rule 63 allows procuring agencies to encourage the inclusion of small and medium enterprises and marginalized groups by according preferences in line with notified Federal Government policies. Rule 64 enables procurement of goods, services and works with reduced environmental impact over their life cycle, subject to applicable Government policy and targets.

Grievance Redressal and Alternative Dispute Resolution

Rule 65 requires a Grievance Redressal Committee (GRC) comprising an odd number of members completely outside the procuring agency, drawn from another procuring agency or the Authority’s pool of experts accessible through EPADS. It deals with complaints arising before the procurement contract comes into force.

A complaint against eligibility parameters, evaluation criteria or bidding-document terms is to be filed two days before the proposal-submission deadline. A complaint after submission of a bid may be filed within seven days of announcement of the technical evaluation report and within five days after issuance of the final evaluation report. The GRC is to decide a complaint within ten days of receipt. An aggrieved party may appeal to the Authority’s Appellate Committee within ten days of communication of the GRC decision, or where the GRC fails to decide within the stipulated period. The Appellate Committee is to decide the appeal within 45 days of receipt.

Rule 66 addresses alternative dispute resolution after a procurement contract has come into force, including arbitration where another ADR method does not lead to an amicable settlement. The pre-contract grievance process and post-contract dispute-resolution provisions should not be confused.

Transition from the Public Procurement Rules, 2004 and Repeal

Rule 68 provides that procurement proceedings initiated before commencement of the 2026 Rules are to be processed under the Public Procurement Rules, 2004. Rule 69 repeals the 2004 Rules. Accordingly, the applicable framework for a procurement depends on when the proceedings were initiated, and not simply on the date on which a later administrative step is taken.

For an ongoing procurement, the procuring agency should retain the record showing the initiation date and apply the transition provision to determine which Rules govern the proceedings. New procurement proceedings are governed by the 2026 Rules, subject to the Ordinance, applicable regulations and any relevant transition or other express provision.

Schedule I — Special Commodity Procurement

Schedule I forms part of the Rules and identifies specified commodities for which particular response-time, bid-validity and grievance-period arrangements apply. The Schedule includes agricultural products such as fertilizer, grains and sugar, and petroleum products. The applicable time periods should be checked against the exact commodity entry in the Schedule and the relevant procurement notice.

How Procuring Agencies Should Apply the 2026 Rules

Before initiating a procurement, the procuring agency should identify the applicable procurement method and threshold, confirm budget availability, include the requirement in the annual procurement plan, prepare non-discriminatory specifications and ensure that the correct committee or validation arrangement is in place. The notice, bidding documents, clarifications, bid receipt and opening, evaluation, award and subsequent contract-management record should be completed through EPADS in accordance with the Rules.

Where an alternative method is proposed, the agency should verify that the precise conditions are met and record the required justification. The financial thresholds in the Rules should not be treated as permission to divide procurement artificially. The agency should also check current PPRA regulations, standard bidding documents and any changes or clarifications issued by the Authority.

Important Note on Applicability and Current Instructions

This post summarizes the Public Procurement Rules, 2026 notified through S.R.O. 1658(I)/2026 on 28 September 2026. It is a reference guide and not a substitute for the Gazette notification, the PPRA Ordinance, 2002, regulations, standard bidding documents or instructions issued by the Authority. The Rules contain detailed exceptions, provisos, procedures and financial conditions that must be read in full before a procurement decision is made.

The Rules apply to Federal Government procuring agencies as stated in Rule 3. Provincial Governments, autonomous bodies and other entities should confirm the procurement law and rules applicable to their own legal status. Procuring agencies should also verify the current version of PPRA regulations, financial thresholds and EPADS procedures before each procurement.

Frequently Asked Questions

When were the Public Procurement Rules, 2026 notified?

They were notified through S.R.O. 1658(I)/2026 dated 28 September 2026 and came into force at once.

Which law authorizes the 2026 Rules?

The Federal Government made them under section 26 of the Public Procurement Regulatory Authority Ordinance, 2002 (Ordinance XXII of 2002).

Do the 2026 Rules apply to Provincial Government procurement?

Rule 3 applies to public procurements made by procuring agencies of the Federal Government, whether within or outside Pakistan. A Provincial Government procurement must be checked against the procurement law and rules applicable to that Province or entity.

What happened to the Public Procurement Rules, 2004?

Rule 69 repeals the 2004 Rules. Under Rule 68, however, procurement proceedings initiated before commencement of the 2026 Rules continue to be processed under the 2004 Rules.

What is the minimum response time for national and international competitive bidding?

Rule 19 prescribes at least 10 days for national competitive bidding and 20 days for international competitive bidding, calculated from publication of the procurement notice on EPADS. The Rule contains a separate minimum response period for requests for quotations under Rule 32(1)(b).

When is publication in newspapers required?

Rule 18 requires procurement opportunities exceeding Rs. 5 million to be published on EPADS and in at least two national dailies, one in English and one in Urdu, in addition to the other publication requirements in the Rule.

Related EmployeesDesk Resources

Download the official Public Procurement Rules, 2026: Public Procurement Rules, 2026 (S.R.O. 1658(I)/2026) — PDF.

For the Gazette notification and the Authority’s online version, consult the official Gazette PDF and the PPRA Rules 2026 page.